Widening of Ridge Road is greenlighted

By
Published:

NEW PORT RICHEY - Drivers headed to Pasco-Hernando Community College's West Campus and other destinations along Ridge Road may begin seeing construction crews in the coming months.

Pasco County officials have given the go-ahead for a contractor to begin widening a section of Ridge Road east of Little Road.

The two-lane Ridge Road will become four lanes along the nearly 3-mile stretch from Broad Street to Moon Lake Road.

Pepper Contracting Services submitted a bid on widening of slightly more than $22 million, county records show.

The Tampa-based contractor has about 15 months, or 450 days, to finish the job. Weather delays or other circumstances could add more than six months to the schedule, or 195 days, under terms of the contract.

A preconstruction meeting with the contractor is scheduled for July 25, said Deborah Bolduc, program administrator for the Pasco County Engineering Services Department.

During the first six months of the project, crews will concentrate on some clearing and grubbing work, installation of silt screen and relocation of utilities.

The wider Ridge Road will end at the Moon Lake Road intersection where the Ridge extension would begin.

The Ridge extension project remains in regulatory limbo. Since the late 1990s, county leaders have envisioned the extension stretching east to Suncoast Parkway in the first phase and then from the toll road to U.S. 41.

Pasco County officials' arguments for the extension as a hurricane evacuation route, however, have not persuaded regulators to give an OK. The U.S. Army Corps of Engineers, which has the job of reviewing the county's permit request for the project under the federal Clean Water Act, received many objections to the proposed extension because it would cross wetlands.